BIM-Anwendungsfall (AwF) Abrechnung-Vortrieb am Beispiel des Zentrums am Berg: BIM use case – Payment of tunnel excavation classes – Example Zentrum am Berg

Robert Wenighofer, Johannes Waldhart, Nina Eder, Katharina Zach

Publikation: Beitrag in FachzeitschriftArtikelForschungBegutachtung

2 Zitate (Scopus)

Abstract

BIM modelling of infrastructure works is controlled by a global market consisting of few software suppliers and is contingent upon the functions provided by them. Customization options furnished by the software suppliers often enable enhancement of functions, which is essential for infrastructure BIM although not completely available. This enables improved interoperability of the software tools used in this area. IFC is most likely to become an established international format for data exchange with its constant but also intricate further development. However, in underground infrastructure construction, both international and national standards are used and the integration of the latter in IFC cannot be anticipated. Hence, the implementation of BIM has to apply national standards in the use cases of collaborative data exchange among the different disciplines in tunnelling. In this contribution, the use case of payment of excavation classes and its implementation in a BIM environment are addressed. It discusses the interoperable interlinkage of software tools commonly used in construction to generate consistent digital data transfer and it underscores the need for an interdisciplinary agreement to integrate national standards into adequate practice for the implementation of BIM.

Titel in ÜbersetzungBIM use case – Payment of tunnel excavation classes – Example Zentrum am Berg
OriginalspracheDeutsch
Seiten (von - bis)237-248
Seitenumfang12
FachzeitschriftGeomechanics and tunnelling = Geomechanik und Tunnelbau
Jahrgang13:2020
Ausgabenummer2
DOIs
PublikationsstatusVeröffentlicht - 1 Apr. 2020

Bibliographische Notiz

Publisher Copyright:
© 2020, Ernst und Sohn. All rights reserved.

Dieses zitieren