Abstract
The railbound concrete supply for the inner lining of long railway tunnels poses a considerable logistical challenge. Due to long transport distances and possible complex time schedules, a thourogh planning as well as ongoing optimisations of the logistics concept are essential. Based on the construction site Koralmtunnel KAT 2, this thesis investigates the development of a dynamic methodology which uses a module-based programming to calculate necessary supply trips from a given construction schedule. The results are the basis for an overall analysis of the described problem.
| Translated title of the contribution | Optimisation of the supply concept for the inner lining of a long railway tunnel |
|---|---|
| Original language | German |
| Qualification | Dipl.-Ing. |
| Supervisors/Advisors |
|
| Award date | 30 Jun 2017 |
| Publication status | Published - 2017 |
Bibliographical note
embargoed until 10-05-2022Keywords
- railway tunnel
- inner lining
- logistics
- conrete supply